6/11/2018 TayEx is stripping sod and topsoil from the site for Lenz to haul away.
|
![](https://cdnsm5-ss19.sharpschool.com/UserFiles/Servers/Server_1936563/Image/Bond Projects/New SHS/Ph 1 Site Prep/image002.jpg) |
6/21/18 Contouring of the site in progress. Drainage material from the old baseball fields is being stockpiled for use as utility backfill.
|
|
CTB – Concrete Treated Base
|
![](https://cdnsm5-ss19.sharpschool.com/UserFiles/Servers/Server_1936563/Image/Bond Projects/New SHS/Ph 1 Site Prep/image003.jpg) |
6/27/18 The building pad is being treated with cement to stabilize it between phases. The surface is graded, then a spreader distributes a specified quantity of cement over the soil surface, followed by the milling equipment, which tills the cement into the soil at a depth of 12”. Water is added as needed. Another 12” of soil, called a ‘lift’ is spread on top and graded until building pad is at the correct elevation.
|
|
![](https://cdnsm5-ss19.sharpschool.com/UserFiles/Servers/Server_1936563/Image/Bond Projects/New SHS/Ph 1 Site Prep/image004.jpg) |
![](https://cdnsm5-ss19.sharpschool.com/UserFiles/Servers/Server_1936563/Image/Bond Projects/New SHS/Ph 1 Site Prep/image005.jpg) |
Spreader being filled with cement.
|
Mill head.
|
|
![](https://cdnsm5-ss19.sharpschool.com/UserFiles/Servers/Server_1936563/Image/Bond Projects/New SHS/Ph 1 Site Prep/image006.jpg)
|
6/28/18 Portable demolition in progress. Debris is placed in a container and removed to be sorted for recycle.
|
|
Soldier Pile Wall
|
![](https://cdnsm5-ss19.sharpschool.com/UserFiles/Servers/Server_1936563/Image/Bond Projects/New SHS/Ph 1 Site Prep/image007.jpg) |
7/2/18 Steel for the soldier pile wall has arrived on site
|
![](https://cdnsm5-ss19.sharpschool.com/UserFiles/Servers/Server_1936563/Image/Bond Projects/New SHS/Ph 1 Site Prep/image008.jpg)
|
|
7/2/18 Drilling for pile placement. Holes will be 40’ to 45’ deep.
|
|
![](https://cdnsm5-ss19.sharpschool.com/UserFiles/Servers/Server_1936563/Image/Bond Projects/New SHS/Ph 1 Site Prep/image009.jpg) |
![](https://cdnsm5-ss19.sharpschool.com/UserFiles/Servers/Server_1936563/Image/Bond Projects/New SHS/Ph 1 Site Prep/image010.jpg) |
Blue, clayey soils being removed.
|
Finished hole
|
|
![](https://cdnsm5-ss19.sharpschool.com/UserFiles/Servers/Server_1936563/Image/Bond Projects/New SHS/Ph 1 Site Prep/image011.jpg) |
![](https://cdnsm5-ss19.sharpschool.com/UserFiles/Servers/Server_1936563/Image/Bond Projects/New SHS/Ph 1 Site Prep/image012.jpg) |
7/2/18 Placing soldier piles.
|
|
![](https://cdnsm5-ss19.sharpschool.com/UserFiles/Servers/Server_1936563/Image/Bond Projects/New SHS/Ph 1 Site Prep/image013.jpg) |
![](https://cdnsm5-ss19.sharpschool.com/UserFiles/Servers/Server_1936563/Image/Bond Projects/New SHS/Ph 1 Site Prep/image014.jpg) |
Tack welding lagging anchors in place.
|
Removing the dirt for the next 4’ round of lagging. Lagging is installed from the top of the wall down.
|
|
![](https://cdnsm5-ss19.sharpschool.com/UserFiles/Servers/Server_1936563/Image/Bond Projects/New SHS/Ph 1 Site Prep/image015.jpg) |
Stanwood Redi-Mix on site delivering CDF (Controlled Density Fill) to fill the pile holes after the piles are placed.
|
|
|
![](https://cdnsm5-ss19.sharpschool.com/UserFiles/Servers/Server_1936563/Image/Bond Projects/New SHS/Ph 1 Site Prep/image016.jpg) |
8/6/18 Soldier pile wall and CTB complete at the future Athletics wing of the building.
|
|
Storm Detention System
|
![](https://cdnsm5-ss19.sharpschool.com/UserFiles/Servers/Server_1936563/Image/Bond Projects/New SHS/Ph 1 Site Prep/image017.jpg)
|
|
6/26/18 Early excavation of the storm detention facility.
|
|
![](https://cdnsm5-ss19.sharpschool.com/UserFiles/Servers/Server_1936563/Image/Bond Projects/New SHS/Ph 1 Site Prep/image018.jpg) |
![](https://cdnsm5-ss19.sharpschool.com/UserFiles/Servers/Server_1936563/Image/Bond Projects/New SHS/Ph 1 Site Prep/image019.jpg) |
6/28/18 Progress
|
7/5/18 Progress
|
|
![](https://cdnsm5-ss19.sharpschool.com/UserFiles/Servers/Server_1936563/Image/Bond Projects/New SHS/Ph 1 Site Prep/image020.jpg) |
![](https://cdnsm5-ss19.sharpschool.com/UserFiles/Servers/Server_1936563/Image/Bond Projects/New SHS/Ph 1 Site Prep/image021.jpg) |
7/10/18 Spreading pea gravel bedding.
|
7/16/18 CMP (Corrugated Metal Pipe) delivered to the job site.
|
|
![](https://cdnsm5-ss19.sharpschool.com/UserFiles/Servers/Server_1936563/Image/Bond Projects/New SHS/Ph 1 Site Prep/image022.jpg) |
![](https://cdnsm5-ss19.sharpschool.com/UserFiles/Servers/Server_1936563/Image/Bond Projects/New SHS/Ph 1 Site Prep/image023.jpg) |
7/16/18 Work begins placing and joining the CMP.
|
7/24 Progress
|
|
![](https://cdnsm5-ss19.sharpschool.com/UserFiles/Servers/Server_1936563/Image/Bond Projects/New SHS/Ph 1 Site Prep/image024.jpg) |
|
7/25/18 The storm detention system is nearly complete.
|
7/30/18 Backfill and compaction begins at west end of system.
|
|
![](https://cdnsm5-ss19.sharpschool.com/UserFiles/Servers/Server_1936563/Image/Bond Projects/New SHS/Ph 1 Site Prep/image026.jpg) |
|
8/9/18 Backfill nearing completion. The storm detention system will be completely covered with 3’ to 8’ of fill and the staff parking area and bus loop will be built over the top.
|
|
|
|
|
|